C.2 System Testing & Checkout
C.2.1 Initial Display Testing
The G900X system is tested while operating in the normal mode unless otherwise specified. Restart the
PFD by cycling the PFD circuit breaker to start the display in the normal mode. Cycle power to the MFD
in the same manner.
1.
Look at the MFD power-up screen (see Figure C-12). In the upper right corner, the display shows the
Model and System Software Version.
Figure C-12. Example MFD Power Up Page
2.
This ‘System’ number is the System Software Version. It correlates to the G900X SW Loader
Card Image used to load the software to the system. For example:
EXAMPLE:
System Software Version ‘
0718.00
’ = Loader Card Image P/N 006-B
0718-00
3.
Verify that the System Software Version is correct.
4.
Press the ENT key to acknowledge the agreement on the MFD (NOTE: The rightmost softkey
may also be used to acknowledge the agreement).