CX250 S2
Upgrade and Maintenance Manual
179
Main memory
7.3
Removing memory modules
7.3.1
Required tools
●
Preliminary and concluding steps: tool-less
●
Main steps: tool-less
7.3.2
Preliminary steps
Perform the following procedures:
Ê
"Disabling SVOM boot watchdog functionality" on page 65
Ê
Locate the desired server node.
Ê
"Shutting down the server node" on page 45
Ê
If applicable, remove all external cables from the server node.
Ê
"Removing the server node from the server enclosure" on page 46
Ê
Disconnect the SATA cable(s) from the connectors on the system board
described in section
"Connectors on the boards" on page 251
,
figure 150
and take it out of the chassis.
Ê
If a BBU is installed disconnect the BBU cable from the BBU connector on
the mezzanine SAS RAID controller described in section
"Connectors on the
boards" on page 251
,
figure 152
and take it out of the chassis.
Ê
"Removing the memory slot air ducts" on page 60
Ê
Identify the desired memory slot according to the mounting order described
in section
"Memory sequence" on page 172
.
Upgrade and Repair Units (URU)
Average task duration: 5 minutes
Summary of Contents for Primergy CX250 S2
Page 6: ...Upgrade and Maintenance Manual CX250 S2 ...
Page 16: ...16 Upgrade and Maintenance Manual CX250 S2 ...
Page 20: ...20 Upgrade and Maintenance Manual CX250 S2 Introduction ...
Page 30: ...30 Upgrade and Maintenance Manual CX250 S2 Before you start ...
Page 44: ...44 Upgrade and Maintenance Manual CX250 S2 Important information ...
Page 184: ...184 Upgrade and Maintenance Manual CX250 S2 Main memory ...
Page 244: ...244 Upgrade and Maintenance Manual CX250 S2 System board and components ...
Page 254: ...254 Upgrade and Maintenance Manual CX250 S2 Cabling ...