4. Commissioning
4−8
Festo P.BE−CPX−CMA X−SYS−EN en 0908NH
4.2
Preparations for commissioning
4.2.1
Checking the axis string
Prior to commissioning:
·
Check the complete system structure, especially the drive
tubing connections and the electrical installation (see
chapters 2 and 3).
It is possible to pre−parameterize the CMAX even without the
components on the axis interface.
4.2.2
Switching on the power supply, switch−on behaviour
Warning
High acceleration forces on the connected actuators! Unex
pected motions can cause collisions and severe injuries.
·
Switching on:
Always first switch on the valve load voltage supply and
then the compressed air supply.
·
Switching off:
Before mounting, installation and maintenance work, put
the system into a safe state (e.g. by putting the drive in a
safe position and deactivating the controller).
Always make sure that the compressed air and valve load
voltage supplies are switched off and locked before
working in the machine area.
Summary of Contents for CPX-CMAX-C1-1
Page 2: ......
Page 22: ...Contents and general safety instructions XX Festo P BE CPX CMAX SYS EN en 0908NH...
Page 23: ...CMAX system overview 1 1 Festo P BE CPX CMAX SYS EN en 0908NH Chapter 1...
Page 31: ...Fitting and pneumatic installation 2 1 Festo P BE CPX CMAX SYS EN en 0908NH Chapter 2...
Page 60: ...2 Fitting and pneumatic installation 2 30 Festo P BE CPX CMAX SYS EN en 0908NH...
Page 61: ...Electrical installation 3 1 Festo P BE CPX CMAX SYS EN en 0908NH Chapter 3...
Page 79: ...Commissioning 4 1 Festo P BE CPX CMAX SYS EN en 0908NH Chapter 4...
Page 122: ...4 Commissioning 4 44 Festo P BE CPX CMAX SYS EN en 0908NH...
Page 123: ...Diagnostics and error handling 5 1 Festo P BE CPX CMAX SYS EN en 0908NH Chapter 5...
Page 163: ...Technical appendix A 1 Festo P BE CPX CMAX SYS EN en 0908NH Appendix A...
Page 176: ...A Technical appendix A 14 Festo P BE CPX CMAX SYS EN en 0908NH...