4. Commissioning
4−41
Festo P.BE−CPX−CMA X−SYS−EN en 0908NH
4.6.2
Start record
SCON.ENABLED = 1
SCON.OPE N = 1
[m]
SCON.ACK = 1
Wait time
1 bus cycle
CPOS.START = 1
CPOS.START = 0
Record executed
SCON.ACK = 0
[m]
[m]
[m]
[m]
[m]
Enable operation
CPOS.START = 0
Output data byte 3
= Target record number
[o]
SCON.ACK = 1
SCON.ACK = 0
SCON.ACK = 0
SCON.ACK = 1
SCON.MC = 0
SCON.MC = 1
Preparing the starting edge
Starting edge
For all fieldbuses which do not support consistent data transmission, after entering the
record number, one bus cycle must be waited, during which the record number is
transferred to the CMAX on the fieldbus.
Recommendation: On most controls, the PLC cycle is longer than the bus cycle.
> Wait time = 1 PLC cycle
Reset start to reduce the wait time for the next time.
MC must only be waited for when the target position
must be reached for the further sequence.
[m]
[o]
It is imperative that this action
be executed.
This action is a recommendation.
It does not have to be executed.
[m]
[o]
Summary of Contents for CPX-CMAX-C1-1
Page 2: ......
Page 22: ...Contents and general safety instructions XX Festo P BE CPX CMAX SYS EN en 0908NH...
Page 23: ...CMAX system overview 1 1 Festo P BE CPX CMAX SYS EN en 0908NH Chapter 1...
Page 31: ...Fitting and pneumatic installation 2 1 Festo P BE CPX CMAX SYS EN en 0908NH Chapter 2...
Page 60: ...2 Fitting and pneumatic installation 2 30 Festo P BE CPX CMAX SYS EN en 0908NH...
Page 61: ...Electrical installation 3 1 Festo P BE CPX CMAX SYS EN en 0908NH Chapter 3...
Page 79: ...Commissioning 4 1 Festo P BE CPX CMAX SYS EN en 0908NH Chapter 4...
Page 122: ...4 Commissioning 4 44 Festo P BE CPX CMAX SYS EN en 0908NH...
Page 123: ...Diagnostics and error handling 5 1 Festo P BE CPX CMAX SYS EN en 0908NH Chapter 5...
Page 163: ...Technical appendix A 1 Festo P BE CPX CMAX SYS EN en 0908NH Appendix A...
Page 176: ...A Technical appendix A 14 Festo P BE CPX CMAX SYS EN en 0908NH...