J.12.420.00.03, eliminate play and secure the cables with clamping
bolts M5x5 in clamps J.12.412.05.03 (Pic. 9.4.2.7). Secure the bolts
with LOCTITE 262.
8. The regulators J.12.412.05.03 on the intermediate bracket
J.12.420.00.03 should be screwed in gradually until the cables are
properly tightened and then secured with nuts.
9. Turn the bracketJ.12.422.00.03 to the left in the end stops direction. Set
the levers in the aft position (to the end stops). Clamp the cables in the
lever with bolts M5x5 (Pic. 9.4.2.1). The bolts should be secured with
LOCTITE 262.
Pic. 9.4.2.9
J.12.412.05.03
J.12.431.00.03
J.12.431.00.03
J.12.431.00.03
J.12.412.05.03