1.
2.
3.
4.
5.
6.
7.
-
a.
-
b.
8.
-
-
-
-
-
9.
1.5 Start-up Quick Guide
Do at minimum these procedures during the installation and commissioning.
If there are problems, speak to the local distributor.
Vacon Ltd is not responsible for the use of the AC drives against the instructions.
Procedure
Check that the delivery agrees to the order, see
Before starting the commissioning, read carefully the safety instructions in
.
Before the mechanical installation, check the minimum clearances around the AC drive (
5.2.3 Cooling of Standalone AC drives (FR10 to FR11)
) and check the ambient conditions in
Check the dimensions of the motor cable, mains cable, mains fuses and check the cable connections. Read
6.2 EMC-compliant Installation
Obey the installation instructions, see
Find information on the control connections in
7.3.2 Control Terminals on OPTA1
If the start-up wizard is active, select the language of the control panel and the application. Accept the selections with the
[enter] button. If the start-up wizard is not active, obey the instructions a and b.
Select the language of the control panel from the Menu M6, page 6.1. For instructions, see
.
Select the application from the Menu M6, page 6.2. For instructions, see
8.7.4 Changing the Application
.
All parameters have factory default values. To make sure that the AC drive operates correctly, make sure that these group
G2.1 parameters have the same data as the nameplate. For more information on the parameters in the list, see the VACON
®
All in One Application Manual.
Nominal voltage of the motor
Nominal frequency of the motor
Nominal speed of the motor
Nominal current of the motor
Motor cos phi
Obey the commissioning instructions, see
9.2 Commissioning the AC Drive
.
The VACON
®
NXS/NXP AC drive is ready for operation.
AQ275638903263en-000601 / DPD00910 | 11
Danfoss A/S © 2022.12
Introduction
VACON® NXS/NXP Air-cooled
Operating Guide