1.1 Procedure and Outline
Follow the following procedure to conduct the initial test operation after installation.
1.1.1 Check Work Prior to Turn Power Supply On
1.1.2 Turn Power On
(V3180)
Check on amount of refrigerant
charge
Check on refrigerant piping
Check the below items.
2
Power wiring
2
Control transmission wiring
between units
2
Earth wire
Is the power supply three-phase 380-415V / 50Hz?
Have you finished a ductwork to drain?
Have you detach transport fitting?
Is the wiring performed as specified?
Are the designated wires used?
Is the grounding work completed?
Use a 500V megger tester to measure the insulation.
2
Do not use a megger tester for other circuits than 380-415V circuit.
Are the setscrews of wiring not loose?
Is the electrical component box covered with an insulation cover
completely?
Is pipe size proper? (The design pressure of this product is
4.0MPa.)
Are pipe insulation materials installed securely?
Liquid and gas pipes need to be insulated. (Otherwise causes
water leak.)
Are respective stop valves on liquid and gas line securely open?
Is refrigerant charged up to the specified amount?
If insufficient, charge the refrigerant from the service port of stop
valve on the liquid side with outdoor unit in stop mode after turning
power on.
Has the amount of refrigerant charge been recorded on “Record
Chart of Additional Refrigerant Charge Amount”?
(V3056)
"
Be sure to turn the power on 6 hours before starting operation to
protect compressors.
"
Close outside panels of the outdoor unit.
Turn outdoor unit power on.
Turn indoor unit power on.
Carry out field setting on
outdoor PC board
Summary of Contents for VRVIII-S
Page 1: ...SiENBE34 703 Basic Training Manual R 410A Heat Pump 50Hz Service Manual...
Page 11: ...Introduction SiENBE34 703 x...
Page 113: ...Field Setting SiENBE34 703 102 Test Operation...
Page 207: ...Troubleshooting by Indication on the Unified ON OFF Control SiENBE34 703 196 Troubleshooting...
Page 215: ...Wiring Diagrams SiENBE34 703 204 Appendix 2 3 Indoor Unit FXCQ20 25 32 63M8...
Page 216: ...SiENBE34 703 Wiring Diagrams Appendix 205 FXCQ40 50 80 125M8V3...
Page 217: ...Wiring Diagrams SiENBE34 703 206 Appendix FXFQ25 32 40 50 63 80 100 125P7VE...
Page 218: ...SiENBE34 703 Wiring Diagrams Appendix 207 FXZQ20 25 32 40 50M8V1...
Page 221: ...Wiring Diagrams SiENBE34 703 210 Appendix FXDQ20 25M8V3...
Page 222: ...SiENBE34 703 Wiring Diagrams Appendix 211 FXSQ20 25 32 40 50 63 80 100 125M8V3...
Page 232: ...SiENBE34 703 Option List Appendix 221...
Page 235: ...Example of Connection SiENBE34 703 224 Appendix...
Page 241: ...Method of Replacing the Inverter s Power Transistors Modules SiBE34 703 230 Appendix...
Page 261: ...RXYSQ4 5 6 P7Y1B SiENBE34 703 250 Removal Procedure...