Installation check list: ACU, connectors and wiring
98-150471-A02
Chapter 7: Installation check
7-3
Install
ation check
7.2
Installation check list: ACU, connectors and
wiring
Step
Task
Verification and further
information
Done
1.
Check that the ACU is grounded correctly,
using the mounting bolts and washers.
and
2.
Make sure you strain relieved the cables.
See
3.
Make sure that the VSAT modem is
mounted close to the ACU.
See
4.
Check that the ADU antenna N-connector is
properly connected with the 50 Ohm RF
cable.
Visual inspection of the
cover plate at the bottom
of the ADU.
5.
Check that the ACU antenna N-connector is
properly connected with the 50 ohm RF
cable.
Visual inspection of the
connector panel of the
ACU.
6.
Check that the ACU's
Rx Out
is connected
to the VSAT modem’s Rx in using the
included 1 m F-F 75 ohm cable.
Visual inspection of the
connector panel of the
ACU and the VSAT
modem.
7.
Check that the ACU's
Tx In
is connected to
the VSAT modem's Tx out using the
included 1 m F-F 75 ohm cable.
Visual inspection of the
connector panel of the
ACU and the VSAT
modem.
Table 7-2: Installation check list: ACU, connectors and wiring
SAILOR900HP.book Page 3 Monday, July 18, 2016 12:44 PM