Step 8
Using a laser level, perform initial leveling of the structure by leveling the horizontal cross-bars of all
structures, then tighten all screws.
Tighten all horizontal screws first, then tighten all vertical screws.
Step 9
An alternative leveling method is to place a bubble level on all horizontal cross-bars.
Note
Since the assembly is one unit, take care not to raise the leveling feet off the floor while raising or
lowering the leveling feet.