4.7 Leak Test (LEAK TEST) Task
•
If required, use the
INPUT
key to change pressure units.
•
Set-up the leak test WAIT and DURATION times to the required values as shown below. A
minimum wait period of 3 minutes is recommended.
•
Close the vent valve and pressurize the device/system to the required
LEAK TEST
pressure.
•
Press the
RUN
(F2)
key to start the leak test. When completed, the beeper sounds and the
leak test results are written to the display.
A
External pressure source
B
Pressure regulator
C
Device/system under test
PRESSURE INT
RUN
CHANGE
VALUE
WAIT
DURATION
START PRESS
STOP PRESS
PRESS CHANGE
LEAK RATE
TASK : LEAKTEST
SNAPSHOT MODE
TASK : ADVANCED
SNAPSHOT MODE
PRESSURE INT
CHANGE
VALUE
RUN
CHANGE
VALUE
RUN
SET WAIT TIME
SET DURATION
TASK : ADVANCED
SNAPSHOT MODE
PRESSURE INT
WAIT
180
secs
DURATION 60
secs
START PRESS
STOP PRESS
PRESS CHANGE
LEAK RATE
WAIT 180
secs
DURATION
60
secs
START PRESS
STOP PRESS
PRESS CHANGE
LEAK RATE
Summary of Contents for Druck DPI 610 IS
Page 1: ...Druck com DPI 610 615 IS Intrinsically Safe Portable Pressure Calibrator Instruction Manual...
Page 2: ......
Page 6: ...Copyright 2007 Baker Hughes Company iv DPI 610 615 IS Instruction Manual English...
Page 10: ...Copyright 2007 Baker Hughes Company viii DPI 610 615 IS Instruction Manual English...
Page 75: ......