For the Electrician
Mains connection on pellet boiler
The mains connection power socket has to be moved to the back.
– Remove the covers to the power socket and unscrew the socket – Fig. 148.
– Remove the cable clips (Fig. 148), disconnect the socket completely from the cable and lay the cable under
“cladding 9top” – Fig. 150.
– Remount the socket to the cable (earth in the middle! – Fig. 151) and mount the socket behind the filling pipe
of the water tank – Fig. 152.
– Connect / plug in the mains power plug – Fig. 152.
Fig. 148 Dismount socket
Fig. 149 Loosen cable clips
Fig. 150 Unscrew socket from cable
Lay cable underneath top cladding
Fig. 151 Reconnect socket to cable
Fig. 152 Mount power plug behind filling pipe
green/yellow
earth in the
middle