Centurion Water Heater- Edge [ii]: Install-Operation-Service
SECTION 2: INSTALLATION
OMM-0153_A
• 8/25/2022 Technical Support • (800) 526-0288 • Mon-Fri, 8 am - 5 pm EST Page 12 of 131
SECTION 2:
INSTALLATION
2.1 RECEIVING THE UNIT
Each CENTURION Water Heater is shipped as a single, crated unit. The shipping weight for this
model is approximately 1,850 lbs. (839 kg).
The unit must be moved with proper rigging equipment for safety and to avoid damage. The unit
should be completely inspected for evidence of shipping damage and shipment completeness at
the time of receipt from the carrier and before the bill of lading is signed.
C A U T I O N !
While packaged in the shipping container, the unit must be moved by pallet jack or forklift
from the front only.
NOTE:
PVI is not responsible for lost or damaged freight. Each unit has A Tip-N-Tell indicator
on the outside of the crate, which indicates if the unit has been turned on its side during
shipment. If the Tip-N-Tell indicator is tripped, do not sign for the shipment. Note the
information on the carrier’s paperwork and request a freight claim and inspection by a claims
adjuster before proceeding. Any other visual damage to the packaging materials should also
be made clear to the delivering carrier.
2.2 UNPACKING
Carefully unpack the unit taking care not to damage the unit enclosure when cutting away
packaging materials
After unpacking, make a close inspection of the unit to ensure that there is no evidence of
damage not indicated by the Tip-N-Tell indicator. The freight carrier should be notified
immediately if any damage is detected.
The following accessories come standard with each unit and are either packed separately within
the unit’s shipping container or are factory installed on the unit:
•
ASME Temperature and Pressure Safety Relief Valve (P/N
92065-5
)
•
An 8” Side Air Inlet Adapter (P/N
39184C
)
•
Condensate Drain Trap (P/N
24441C
)
•
A 2” Natural Gas Supply Valve (P/N
123540C
)
When optional accessories are ordered, they may be packed in the unit’s shipping container,
factory installed on the unit, or packed and shipped in a separate container. Any standard or
optional accessories shipped loose should be identified and stored in a safe place until ready for
installation or use.
2.3 SITE PREPARATION
Ensure that the site selected for installation of the CENTURION Water Heater includes:
•
A level
concrete “housekeeping” pad, per the requirements in Section 2.3.3;
•
Access to a natural gas supply as specified in Section 2.8;
•
Access to AC input power specified in Section 2.9.