Figure 4.32 Rear of Top Plenums and sealed cable entrance example
NO.
DESCRIPTION
1
Cable-pass-through side panels
2
PDU/Cable-management brackets
3
Sealed cable entrance
2. Once inside the rack, route the cables through the top plenums or through the cable-pass-
through side panels:
a. Route the cabling down through the cable-entrance openings in the rack Top Panel,
b. Then, route the cables to the front of the racks where you can use the factory-supplied
cable management fingers, Figure 4.34 on page 51, and the field-supplied cable-
management tools you choose.
NOTE: Inter-cabinet routing can be completed using a variety of DCE cable-management accessories.
Vertiv
| SmartRow DCR Installer/User Guide |
49
Содержание SmartRow DCR
Страница 1: ...SmartRow DCR 3 to 6 Rack 20 kW N N 1 and 5 to 10 Rack 36 kW N Cooling Units 60 Hz Installer User Guide...
Страница 6: ...Vertiv SmartRow DCR Installer User Guide 6...
Страница 12: ...Vertiv SmartRow DCR Installer User Guide 12 This page intentionally left blank...
Страница 52: ...Vertiv SmartRow DCR Installer User Guide 52 This page intentionally left blank...
Страница 66: ...Vertiv SmartRow DCR Installer User Guide 66 This page intentionally left blank...
Страница 70: ...Vertiv SmartRow DCR Installer User Guide 70 This page intentionally left blank...
Страница 72: ...Vertiv SmartRow DCR Installer User Guide 72 This page intentionally left blank...
Страница 76: ...Vertiv SmartRow DCR Installer User Guide 76 This page intentionally left blank...
Страница 82: ...Vertiv SmartRow DCR Installer User Guide 82 This page intentionally left blank...
Страница 101: ......