3. Repeat steps 1 and 2 for each power whip until complete.
Figure 4.31 Power whip routing, knockouts, and circuit-breaker connection
NO.
DESCRIPTION
1
Circuit breakers in load-distribution center
2
Whips routed in front of plenum
3
Knockouts in top of Control panel/Fire-suppression system
4.14.3 Routing Network Cables—Ethernet and Fiber-optic
NOTE: Follow best practices for cable routing and management. Refer to SL-11364 for further details.
Route the network cables on the rear of the row.
1. Route the cables into the DCR using the sealed cable-entrance kit, Figure 4.32 on the facing
page.
•
You can use the kit in each rack or you can group all cables into a “main trunk” that
enters through the Network rack.
Vertiv
| SmartRow DCR Installer/User Guide |
48
Содержание SmartRow DCR
Страница 1: ...SmartRow DCR 3 to 6 Rack 20 kW N N 1 and 5 to 10 Rack 36 kW N Cooling Units 60 Hz Installer User Guide...
Страница 6: ...Vertiv SmartRow DCR Installer User Guide 6...
Страница 12: ...Vertiv SmartRow DCR Installer User Guide 12 This page intentionally left blank...
Страница 52: ...Vertiv SmartRow DCR Installer User Guide 52 This page intentionally left blank...
Страница 66: ...Vertiv SmartRow DCR Installer User Guide 66 This page intentionally left blank...
Страница 70: ...Vertiv SmartRow DCR Installer User Guide 70 This page intentionally left blank...
Страница 72: ...Vertiv SmartRow DCR Installer User Guide 72 This page intentionally left blank...
Страница 76: ...Vertiv SmartRow DCR Installer User Guide 76 This page intentionally left blank...
Страница 82: ...Vertiv SmartRow DCR Installer User Guide 82 This page intentionally left blank...
Страница 101: ......