Wise Package Studio Reference
81
Repackaging Applications and Managing Projects
Note
You also can update the project status in Project Setup. When you change the
status in Project Setup, it is changed in the Project Management tab as well,
and vice versa.
Estimated Completion Date
Specify the date on which you expect the project to be completed.
Current Target Date
If you determine that the project will be completed before or after the
estimated completion date, specify the new target date.
Actual Completion Date
This is pre-filled when Status is changed to Complete.
Estimated Hours
Enter the number of hours you estimate the project will take to complete.
Hours Completed
Enter the total number of hours that have been spent on the project. The Enter
actual hours by field in Workbench Preferences determines how the hours are
entered:
If Project is marked, you enter the total number of hours for the project,
updating the entry as work on the project progresses.
If Task is marked, you enter the actual hours for individual tasks and the
total of the task hours is entered here automatically.
See
Entering Time for Tasks
on page 82.
Remaining Hours
After work on the project begins, use this field to record the number of hours of
work that remain. Example: Suppose you originally estimated the project to
take 40 hours, and you’ve completed 20 hours. However, because you know the
remaining tasks will take 30 hours, you enter 30 hours here. This provides a
more realistic number in the % Completed field.
% Completed
If Remaining Hours is blank,
% Completed = Hours Completed / Estimated Hours
If Remaining Hours has a value,
% Completed = Hours Completed / (Hours Com Remaining Hours).
Assigning Users to Tasks in a Project
¾
Enterprise Management Server only.
Repackaging jobs are often performed by a team. (Example: The project manager
creates and assigns the project. An integrator might analyze and customize the existing
package. A repackager might perform the integration testing, and a tester might verify
the package and finish the project.) On the Project Management tab, you can assign
users to specific tasks in a project.
All tasks in the predefined projects are assigned to the user Admin. All tasks in a new
project are initially assigned to the user who created the project.
Security Setup determines whether you have access to the Project Management tab.