Testing
5-14
7110-A2-GB20-00
June 1997
Lamp Test
The Lamp test determines whether all LEDs are lighting and functioning properly.
During the Lamp test, all LEDs blink simultaneously every second. When you
stop the Lamp test, the LEDs are restored to their normal condition.
Ending an Active Test
A test initiated by the user can be ended by the user.
A Test Timeout option is available to automatically terminate a user-initiated
Loopback or Pattern test (as opposed to manually terminating a test) after it
has been running a specified period of time. Refer to
System Options
,
Table A-1.
Test Timeout does not pertain to tests commanded by the:
— Network, such as the network-initiated Line and Payload Loopbacks.
— DTE, such as the DTE-initiated Data Channel Loopback.
On each test screen is a command column. Pressing Return when the cursor
is on the Stop command stops the test.
Use the Abort Tests selection from the Test menu to stop all tests running on
all interfaces, with the exception of network or DTE-initiated loopbacks.
Command Complete appears when all tests on all interfaces have been
terminated.