Evacuate the system as follows:
➤
Connect the filling hose on the low-pressure side of the manometer
station and the service connection of the 3-way directional valve .
Ensure that you connect the end of the filling hose to the service
connection with the pin .
➤
Connect the middle hose of the manometer station to a vacuum
pump with a non-return valve or a vacuum pump with an adapter .
➤
Switch on the vacuum pump until the pressure has dropped
to a measured value of -1 bar . Evacuate the system for roughly
30 minutes .
➤
Close the valve on the low-pressure side of the manometer station
and switch off the vacuum pump .
➤
Observe the measured value . It should remain constant for
10 minutes . If it does not, there is a leak in the refrigerant circuit .
➤
If the manometer display does not reach a constant value of -1 bar,
tighten the connections . Repeat the above procedure to evacuate
the system . If the measured value of -1 bar is still not reached, find
and repair the leak .
➤
When the manometer display shows a constant pressure of -1 bar,
disconnect the hose from the vacuum pump and the service con-
nection of the 3-way directional valve .
➤
Tighten the sealing cap of the service connection of the 3-way
directional valve using a torque wrench to a torque of 18 Nm .
➤
Remove the valve caps of the valve spindles of the 2-way and
3-way directional valves .
➤
Open the two valves using an Allen key (size 4) .
➤
Re-attach the valve caps of the valve spindles for the 2-way and
3-way directional valves .
➤
Check the connections for leaks .