Test parameters
Duration
Duration
[Off, 2 s
… 180 s]
Change
Change status
[YES, NO]
YES: The instrument measures leakage current in two sequential steps
with delay* in between. The phase voltage is firstly applied to the
right live output of the mains test socket and secondly to the left
live output of the mains test socket.
NO: The phase voltage is applied only to the right live output of the
mains test socket.
Delay
*Delay time
[0.2 s … 5 s]
Test limits
H Limit(Ipe)
High Limit (Ipe) [Off, 0.25 mA
… 15.0 mA, Custom ]
Test circuit
Figure 6.45: Ipe leakage
Ipe Leakage measurement procedure
Select the
Ipe Leakage
function.
Set test parameters / limits.
Connect device under test to the instrument (see test circuits above).
Start measurement.
Measurement can be stopped manually or by timer.
Save results (optional).