Delay
*Delay time
[0.2 s … 5 s]
Test limits
H limit(P)
High Limit (P) [Off, 10 W
… 3.50 kW, Custom]
L limit(P)
Low Limit (P) [Off, 10 W
… 3.50 kW, Custom]
H limit(Idiff)
High Limit (Idiff) [Off, 0.25 mA
… 15.0 mA, Custom ]
H limit(Itou)
High Limit (Itou) [Off, 0.25 mA
… 15.0 mA ]
Test circuit
Figure 6.55: Measurement of
Leak’s and Power
Leak’s & Power measurement procedure
Select the
Leak’s & Power
function.
Set test parameters / limits.
Connect device under test to the instrument (see test circuit above).
Start measurement.
Measurement can be stopped manually or by timer.
Save results (optional).