Ring Setup and Testing: Integration Procedures
Fiber Installation
...........................................................................................................................................................................................................................................................
8 - 9
365-372-334 R2.0
Issue 4, November 2004
...........................................................................................................................................................................
Step 23
Verify that LBO has been installed at far end.
...........................................................................................................................................................................
Step 24
At the near end, connect the input optical fiber to the proper OLIU IN
connector.
Requirement:
The FAULT LED on the OLIU extinguishes after
approximately 10 seconds.
...........................................................................................................................................................................
Step 25
Disconnect the fiber cable from the OUT connector on the OLIU at one
end of the span. At the other end, verify that the associated FAULT
LED is flashing, indicating a loss of signal. Reconnect the fiber and
repeat the process for the other direction of transmission.
...........................................................................................................................................................................
Step 26
In order to enable communications with the adjacent Metropolis
®
DMXplore nodes, execute the
ent-fecom
command for main 1 and
main 2.
Select the following options for Main 1 based on work instructions:
dcc-m{1}-1, COM=ENABLED, SIDE={US or NS}
Select the following options for Main 2 based on work instructions:
dcc-m{2}-1, COM=ENABLED, SIDE={US or NS}
Important!
If inconsistent DCC alarms are raised, US and NS
settings may need to be swapped.
...........................................................................................................................................................................
Step 27
Verify proper shelf timing at each node using
RTRV-SYNCN
. To change
timing modes use the
SET-SYNCN
command.
...........................................................................................................................................................................
Step 28
In order to verify proper communications with the adjacent
Metropolis
®
DMXplore nodes, execute the following command from
the
Command Builder
.
RTRV-MAP-NEIGHBOR
Result:
The TIDs and NSAPs of adjacent nodes will be displayed
along with the OLIU and port they are connected to.
Содержание Metropolis DMXplore
Страница 8: ... C O N T E N T S v i i i 365 372 334 R2 0 Issue 4 November 2004 ...
Страница 16: ... T A B L E S x v i 365 372 334 R2 0 Issue 4 Novmeber 2004 Glossary ...
Страница 224: ... Metropolis DMXplore Access Multiplexer Ring Setup and Testing P A R T x x 365 372 334 R2 0 Issue 4 November 2004 ...
Страница 258: ... Laser Safety and Classifications Metropolis DMXplore Optical Specifications A 8 365 372 334 R2 0 Issue 4 November 2004 ...
Страница 270: ... Fiber Cleaning Cleaning Inspecting Optical Connectors B 1 2 365 372 334 R2 0 Issue 4 November 2004 ...
Страница 286: ... Backplane Pin Replacement Replacement Methods D 1 0 365 372 334 R2 0 Issue 4 November 2004 ...
Страница 292: ... Installation Checklist Overview E 6 365 372 334 R2 0 Issue 4 November 2004 ...
Страница 326: ... G L O S S A R Y G L 3 0 365 372 334 R2 0 Issue 4 November 2004 ...