P/N 960-100190RA_Rev. A {EDP #148851}
© 2009, Japan CashMachine Co., Limited
4 - 6
Section 4
VEGA-RC™BankNote Recycler
Disassembly/Reassembly
Clear & Metallic Edge Belt Replace-
ment
To replace the Clear & Metallic Edge Belts,
proceed as follows:
1. Install the Right Frame Body Shaft (R)
(See Figure 4-16 a) and the Left Frame Body
Shaft (L) (See Figure 4-16 b) with both sets
of Belts attached to the VEGA-RC Unit.
2. Route the Belts from the Frame Body Shafts
to the Main Bobbin as shown in Figure 4-
17a.
3. Reattach the ends of the Belts to the Main
Bobbin using the Retainer Clips (See Figure
4-17 b).
4. Pull on the Belts to obtain some slack and
then re-install the Tray (See Figure 4-18 a)
and the Tray Cover (See Figure 4-18 b).
(Refer to “Clear & Metallic Edge Belt
Removal” on page 4-4).
5. Withdraw the Belts and reassemble the
Course Reversing Assembly (See Figure 4-
19 a). (Refer to “Clear & Metallic Edge Belt
Removal” on page 4-4).
6. Pull out on the Belts to obtain some slack,
and then re-install the Course Reversing
Assembly for proper placement (Review
Figure 4-18).
As a final check, verify that the Belts are
installed and routed correctly as shown in
Figure 4-19.
To re-assemble any other component assemblies in
this procedure, simply reverse the existing disas-
sembly instructions provided here.
a
b
c
Figure 4-16
Frame Body Shaft Assy. Installation
NOTE: Be sure to install the Metallic
Silver Edged Belt onto the correct Bobbin
as indicated by Figure 4-16 c.
NOTE: Ensure that the edges of the Belts
are flush with one another.
a
b
Figure 4-17
Re-attaching the Belts
a
b
Figure 4-18
Tray & Tray Cover Installation
NOTE: After reinstalling the Tray, turn the
Bobbins by hand to take up any excess
slack in the Belts. This will make re-
installation of the Tray Cover easier.
Figure 4-19
Clear and Metallic Belt Installation
Order