4 Planning and installation – Installing the heating system
40
I
NSTALLING
THE
BOILER
1.
Remove the packaging from the boiler.
T
RANSPORTING
WITH
A
PALLET
TRUCK
2.
Transport the boiler to its installation site.
3.
Set down the boiler with the pallet at the planned location while
observing the minimum clearances.
✎
See “4.1 Dimensions”, section “Required room sizes and minimum
clearances” in this chapter.
4.
Remove the two side slats (1) from the pallet.
Caution!
Danger from suspended loads
The boiler weighs over 600 kg. If the boiler is dropped during trans-
port, persons can be seriously injured and the boiler can be dam-
aged.
Make sure that you use appropriate lifting gear when placing the
boiler.
The boiler packaging can be taken to the local recycling company.
Important!
When using the installation aid, observe the required minimum
clearance of 60 cm to the side walls in order to be able to later re-
move the aid.
Also observe the minimum clearance of 150 cm in front of and be-
hind the boiler so that you can remove the pallet.
The final installation position of the boiler must be adjusted after-
wards if necessary.
Figure 4/5 - Undo the pallet attachments
2
1
Содержание Compact 25
Страница 1: ...hdg bavaria com HDG Compact 25 35 HDG Compact 45 50 65 HDG Compact 80 Operating manual ...
Страница 2: ......
Страница 6: ...Operation Manual HDG Compact 25 80 Content 6 ...
Страница 107: ......