gaitway-3D Service manual
Ref.:TM-MAN-0005-ARS
Iss.: A
Rev.: 9
Date: 07/12/2020
Page : 25
Test Step
Measurements/Test Results
Seq.
No.
Description
Required/No
minal (incl.
tolerance)
Measured/
Calculated
Remarks/Calculations
Pass/
No
pass
17.
Check that the Treadmill-spacer-back parts
are in place at the
BACK
of the treadmill and
lift the treadmill to place it on the wheel
boards. Lift
FRONT
side first.
Spacers at:
BACK
First side lifted:
FRONT
Spacers at:
First side lifted:
18.
Move the treadmill away.
19.
Drill the 26 holes in the floor using the
hole-pattern.
For mechanical anchorages, drill 12 mm
diameter holes at a depth of 44mm.
For chemical anchorages, drill 16mm
diameter holes at a depth of 80mm.
Hole diameter:
12 or 16 mm
Hole depth:
44 or 80 mm
Hole diam.:
Hole depth:
Hole-pattern
20.
Clean the holes by blowing air.
Air pump
21.
Insert 26 anchorages in the drilled holes.
For mechanical anchorages, use HILTI HKD
M10x40 and hammer them with the specific
tool.
For chemical anchorages, use HILTI HIT-IC
M10x80 with mortar HILTI HIT-MM PLUS
330/1.
Anchorage:
Mechanical
Or
Chemical
Anchorage:
For mechanical anchorages:
26x Anchorage mechanical
Specific hammer tool
For chemical anchorages:
26x Anchorage chemical
Injection mortar