Site Circuit Breaker
It is recommended that the branch circuit breaker for the machine be readily accessible.
2-2-2-4
Site Power Outlets
A dedicated AC power outlet must be within reach of the unit without extension cords. Other adequate
outlets for the external peripherals, medical and test equipment needed to support this unit must also
be present within 1 m (3.2 ft.) of the unit. Electrical installation must meet all current local, state, and
national electrical codes.
2-2-2-5
Unit Power Plug
If the unit arrives without a power plug, or with the wrong plug, you must contact your GE dealer or the
installation engineer must supply what is locally required.
2-2-2-6
Power Stability Requirements
Voltage drop-out
Max 10 ms.
Power Transients
(All applications)
Less than 25% of nominal peak voltage for less than 1 millisecond for any type of transient, including
line frequency, synchronous, asynchronous, or aperiodic transients.
CAUTION
POWER OUTAGE MAY OCCUR.
The LOGIQ™ 9 requires a dedicated single branch circuit. To avoid circuit overload and
possible loss of critical care equipment, make sure you DO NOT have any other equipment
operating on the same circuit.