4.3.3. Checking the Firmware Version
(1) Purpose
1) Failing to use the proper versions of the A/D board firmware and capture board firmware
with the CXDI application can result in an error, and system operation cannot be
guaranteed. Therefore, the versions of the firmware must be checked to ensure that they
are correct.
(2) Notes
1) This check should always be performed at installation, and if necessary, the firmware
versions should be upgraded.
2) This check cannot be performed with only the control PC. Connect the imaging units and
other equipment, and start up in the normal imaging status.
(3) Procedure
1) Connect the keyboard and mouse to the control PC.
2) Use the capture board interface cable to connect P1 on the capture board to PORT1
(COM3) on the serial board.
* For more information, see “Hyper Terminal Setting”
3) Start up the CXDI system
* Start up the CXDI application.
Note that if the CXDI application does not start up, the version number information
displayed in step 13 is the information read from the A/D board at the last startup.
4) When the normal imaging screen (ignore if an error message is displayed) is displayed on
the operation unit, use the keyboard to enter debugging mode. (Use [Alt] + [Tab].)
5) “Welcome to CCR” is displayed. Select “8- Exit”
6) This returns you to Windows NT. Start up HyperTerminal, and make the settings for the
new connection. For more information on connections, see “Hyper Terminal Setting”.
7) After making the HyperTerminal settings, press the [Enter] key on the keyboard.
* In the following steps, always press the [Enter] key after making the keyboard input.
Содержание CXDI-31
Страница 11: ...Labels and Markings Rear iii ...
Страница 14: ...Labels and Markings Rear vi ...
Страница 18: ......
Страница 20: ......
Страница 34: ...2 Installation Manual No 7 No Name E O power connector guard Name Remarks Remarks Table 3 8 ...
Страница 37: ...2 Installation Manual 4 Installation 4 1 Connecting the units 4 1 1 Connecting block diagram Fig 1 11 ...
Страница 46: ...2 Installation Manual 20 2 Set up on the left side Screw x 4 on the E O box Fig 9 Fig 10 ...
Страница 150: ...2 Installation Manual 124 8 External Dimensional Diagram 8 1 CXDI 31 8 1 1 Imaging unit Fig 1 8 1 2 E O Box Fig 2 ...
Страница 151: ...2 Installation Manual 125 8 1 3 Storage Box Fig 3 ...
Страница 152: ...2 Installation Manual 126 8 2 Option 8 2 1 Grid L 21 8mm 4 1 22 3mm 8 1 22 5mm 10 1 Fig 4 ...
Страница 157: ...3 CXDI 31 Imaging Unit 1 1 Unit Diagram Fig 1 DC DC Conversion Board ...
Страница 184: ......
Страница 186: ......
Страница 187: ...4 CXDI 31 E O Box 1 CXDI 31 E O Box Unit Diagram Fig 1 1 ...
Страница 195: ...4 CXDI 31 E O Box 2 CXDI 31 I F PCB Dip Switch SW1 Fig 5 No change SW 2 1 OFF 2 OFF 3 OFF 4 OFF Fig 6 9 ...
Страница 198: ......