2 Installation Manual
- 114 -
E) The sensors are set to READY status a few seconds after the first irradiation ends, so
continue and perform the second, third and fourth irradiations.
(Perform four irradiations to test whether the Pre Delay time is stable in Phase1.)
[Phase1 complete screen]
[Fig.7]
Check the stability of the pre-delay in Phase1 and determine the X-ray time-out value (internal
parameter) to be used for Phase2.
(The Phase1 measurement results are saved in the [phase1.ers] file.)
This example shows the X-ray irradiation time to be used in Phase2 as 172 msec, but the
irradiation time often cannot be set on the X-ray generator side in such fine increments.
In these cases, set the closest value (180 or 200 msec) that can be used for irradiation.
A = maximum Pre Delay measurement value
Xtmo = A + 10 msec
Irradiation time used in Phase2 = Xtmo + 100 msec
Содержание CXDI-31
Страница 11: ...Labels and Markings Rear iii ...
Страница 14: ...Labels and Markings Rear vi ...
Страница 18: ......
Страница 20: ......
Страница 34: ...2 Installation Manual No 7 No Name E O power connector guard Name Remarks Remarks Table 3 8 ...
Страница 37: ...2 Installation Manual 4 Installation 4 1 Connecting the units 4 1 1 Connecting block diagram Fig 1 11 ...
Страница 46: ...2 Installation Manual 20 2 Set up on the left side Screw x 4 on the E O box Fig 9 Fig 10 ...
Страница 150: ...2 Installation Manual 124 8 External Dimensional Diagram 8 1 CXDI 31 8 1 1 Imaging unit Fig 1 8 1 2 E O Box Fig 2 ...
Страница 151: ...2 Installation Manual 125 8 1 3 Storage Box Fig 3 ...
Страница 152: ...2 Installation Manual 126 8 2 Option 8 2 1 Grid L 21 8mm 4 1 22 3mm 8 1 22 5mm 10 1 Fig 4 ...
Страница 157: ...3 CXDI 31 Imaging Unit 1 1 Unit Diagram Fig 1 DC DC Conversion Board ...
Страница 184: ......
Страница 186: ......
Страница 187: ...4 CXDI 31 E O Box 1 CXDI 31 E O Box Unit Diagram Fig 1 1 ...
Страница 195: ...4 CXDI 31 E O Box 2 CXDI 31 I F PCB Dip Switch SW1 Fig 5 No change SW 2 1 OFF 2 OFF 3 OFF 4 OFF Fig 6 9 ...
Страница 198: ......