Installation & Start-Up | 3-21
3. Perform a leak (pressure) check to ensure there are no leaks in the sys-
tem, then return to this procedure and complete the remaining start-
up and verification tests.
To perform the leak check, follow the procedure under “Sample Sys-
tem Leak Check,” later in this chapter.
4. After the leak check has been performed and has passed, close the
Bench Heater
fuse and
Oven Heater
fuse (if Oven/Sample System
Enclosure is heated) to apply power to the Measuring Cell and Oven
Heater temperature-control zone circuitry.
No alarms will be displayed on the
HOME
screen or entered into the
Alarm Log
until AFTER the system has left the
Not Ready
state
for the first time after power-up, which occurs after the entire sample
system has reached normal operating temperature and has stabilized
(2–3 hours).
5. While performing the remaining start-up tests, close the analyzer
doors to allow the sample system to warm up to normal operating
temperature (necessary only if Oven/Sample System Enclosure is
heated).
The Oven and the rest of the sample system will reach normal operat-
ing temperature (application-specific) in approximately 2 hours, but
may take up to another hour to stabilize.
To minimize the time it takes for the entire sample system to warm
up to normal operating temperature, be sure to close the doors after
performing the checks that require them to be open.
6. While working from the User Interface Panel, perform the following
checks to ensure the analyzer temperature-control zone circuitry is
operating properly and the system pressures are set appropriately.
Record the temperature value for each zone and the system pressures
to use as a reference later while comparing the values.
For instructions on working from the User Interface Panel, refer to
Chapter 4.
If changes need to be made to any of the parameters settings, a pass-
word must be entered to allow the changes to be made. For details
about entering a password, refer to “Login/Set Passwords Screen” in
Chapter 4.
NOTE
NOTE
NOTE
Содержание IPS-4-UV
Страница 15: ...Contents xv...
Страница 16: ...xvi IPS 4 UV Analyzer GPDiv2 This page intentionally left blank...
Страница 24: ...1 8 IPS 4 UV Analyzer GPDiv2 This page intentionally left blank...
Страница 66: ...3 36 IPS 4 UV Analyzer GPDiv2 This page intentionally left blank...
Страница 138: ...5 32 IPS 4 UV Analyzer GPDiv2 Figure 5 4 Over Temperature alarm Reset Switch S501 Relay board 100 1942...
Страница 144: ...6 6 IPS 4 UV Analyzer GPDiv2 This page intentionally left blank...
Страница 180: ...A 2 IPS 4 UV Analyzer GPDiv2 Analyzer Light Path Schematic...
Страница 183: ...Appendix Drawings A 5 Detector Interface Board 100 1937...
Страница 184: ...A 6 IPS 4 UV Analyzer GPDiv2 Detector Board 100 1955...
Страница 185: ...Appendix Drawings A 7 Display Interface Board 100 1978...
Страница 186: ...A 8 IPS 4 UV Analyzer GPDiv2 Customer Connection Board 100 1971...
Страница 187: ...Appendix Drawings A 9 Relay Board 100 1942...
Страница 188: ...A 10 IPS 4 UV Analyzer GPDiv2 Analog Board 100 1922...
Страница 189: ...Appendix Drawings A 11 MCU Board 100 1914...
Страница 190: ...A 12 IPS 4 UV Analyzer GPDiv2 Xenon Lamp Board 100 2061...
Страница 191: ...Appendix Drawings A 13 Electronics Enclosure Wiring Diagram Sheet 1 of 3 WX 102877...
Страница 192: ...A 14 IPS 4 UV Analyzer GPDiv2 Electronics Enclosure Wiring Diagram Sheet 2 of 3 WX 102877...
Страница 193: ...Appendix Drawings A 15 Electronics Enclosure Wiring Diagram Sheet 3 of 3 WX 102877...
Страница 194: ...A 16 IPS 4 UV Analyzer GPDiv2 This page intentionally left blank...
Страница 196: ...S 2 IPS 4 UV Analyzer GPDiv2 This page intentionally left blank...
Страница 200: ...G 4 IPS 4 UV Analyzer GPDiv2 g 1035 17 32 Not used 1036 Not used 1037 Not used 1038 Not used 1039 Not used...