1. System Installation Requirements
1-2
TI 33J01J10-01EN
1.1
Control Room Design
The control room, in which the system control equipment is to be installed, should be
designed in accordance with the following conditions:
n
General
In designing a control room, ensure adequate floor strength and air conditioning including dust,
and moisture-proofing.
SEE
ALSO
• 1.1 Control Room Design
Air Conditioner
• 1.2 Control Room Environment
Air Purity
Installation Environment Specifications
n
Floor Strength and Space
The floor should have adequate strength, and you should design the layout in accordance with
the weight and size of equipment to be installed.
SEE
ALSO
• For the maintenance space required, refer to 2.4, “Servicing Area.”
• For the weight and dimensions of standard equipment, refer to “External Dimensions” (SD).
n
Floor Structure
To prevent damage to cables by operators and maintenance equipment, do not lay cables on the
floor.
Lay cables under the floor as follows:
• Provide an “accessible” floor which also facilitates maintenance work.
• Make cable pits under the floor if it is concrete.
n
Flooding- & Dust-proof Floor
To protect equipment and cables, design a flooding-proof floor.
After the cabling is completed, seal all cable conduits using putty to prevent intrusion of dust,
moisture, rats, and insects into the equipment.