Vertiv
|
XTE 802 Series Walk-In-Cabinet (WIC) Description & Installation Manual (631-205-434)
|
Rev. D
71
Elevated WIC and Generator Platform Installation (P/N D1000-0010-0089-04,
P/N D1000-0010-0089-06, P/N D1000-0010-0089-08, P/N D1000-0010-0089-10,
P/N D1000-0010-0089-12)
This foundation kit is to be used in flood zones and areas where the site needs to be elevated between 4 feet
and 20 feet off the ground. See
Figure 32:
Elevated WIC and Generator Platform Foundation Kit
Elevated WIC and Generator Platform Installation Procedure
1.
Assemble the universal driving tool on the correct Kelly bar adapter.
2.
Connect Kelly bar adapter to the Kelly bar on the drive head.
3.
Move drive tool assembly to the first helical and attach the universal driving tool to the helical plate
paying attention to keeping the Kelly bar as centered in the helical as possible. The leveling hardware
can be used for this temporary attachment.
4.
Lift helical upright allowing it to swing free of the ground.
5.
Maneuver the helical directly over the installation point.
6.
Lower the helical until the point of the helical is forced into the ground and on target.
7.
Screw the helical 12 inches into the ground and plumb using a level on 2 sides 90 degrees from each
other.
8.
Continue screwing the helical into the ground while correcting the Kelly bar's orientation so the helical
embeds itself straight. A ground man can be of assistance in keeping the foundation plumb during the
installation.
9.
Drive the helical until the helical plate is 8 inches above grade, stop the driving tool assembly.
Disconnect the universal driving tool from the helical plate.