XTE 802 Series Walk-In-Cabinet (WIC) Description & Installation Manual (631-205-434)
|
Rev. D
67
WIC and Generator Combo Concrete/Gravity Platform Installation Procedure
1.
The Generator On The Ground (Gravity) Foundation Kit ships assembled so lift and set it on grade or
concrete in desired location.
2.
Level the platform by adjusting the leveling hardware between the frame and the nine leveling points.
Start by leveling the four corners first then adjust the remaining leveling points. Once leveling is
achieved secure the hardware.
3.
Install the WIC stairs on the WIC using the provided hardware.
4.
Install the stairs for the generator area of the platform using the provided hardware.
Generator Wings Installation Procedure:
1.
Bolt spacers on to both sides of the platform where the generator will be installed using provided
hardware. Spacers are needed when installing generator wings on the WIC and Generator Combo
Platforms due to the I-Beams.
2.
Bolt the wings onto the spacers on both sides of the platform using provided hardware.
3.
Cut and layout rodent guard on the platform to fit generator foot print.
4.
Lift and set the generator, up to 30 KW, onto the platform and rodent guard then anchor in place.
5.
Connect all conduits and cabling.
Figure 29:
WIC and Generator Combo Concrete/Gravity Platform