11.
Install leveling hardware in the center on each helical. Each helical has one set of leveling hardware and
each set of leveling hardware consists of one threaded rod, four nuts, eight washers, and four lock
washers. See
Figure 20:
Install Leveling Hardware
12.
Install the four corner plates on the leveling hardware, one in each corner. See
Figure 21:
Install Four Corner Plates
13.
Level and secure all the leveling hardware on the corner plates and helicals, paying attention to 67.125
inch centers. The leveling hardware should not be installed outside the 3 inch radius of the helical pipe.
The corner plates have elongated holes for 2 inches of play. There is a lot of room for adjustments to
accomplish the 67.125 inch centers. See
and