Operating Instructions
6-26
Post Load Procedure
1. Make sure all the doors are closed and locked.
2. Make sure the setpoint is at the desired setting.
3. Start the unit.
4. A half hour after loading, defrost the unit by manually initiating a defrost cycle. If the evaporator coil temperature is below
7 C (6 C on units with a TG-V controller; 3 C on units with a TG-IV controller), the unit will defrost. The defrost cycle should
terminate automatically.
TG-VI, MT µP-V AND µP-VI NOTE: A manual defrost function is built into the controller. Press SELECT key (MODE key
on µP-VI) (MANUAL DEFROST key on SR-2/SR-3) to scroll to the dEF screen in the menu display. Then press the ENTER
key to initiate Defrost. The display will briefly show Lod (load) and enter Defrost.
Post Trip Inspection
1. Wash the unit.
2. Check for fluid leaks.
3. Check for loose or missing hardware.
4. Check for physical damage to the unit.
Summary of Contents for SLXi Spectrum
Page 17: ...Safety Precautions 2 5 Warning Decals...
Page 18: ...Safety Precautions 2 6 Warning Decals Information Decals...
Page 74: ...Unit Description 5 30...
Page 128: ...Controller Operation 7 28...
Page 156: ...Electrical Maintenance 8 28...
Page 234: ...Refrigeration Maintenance 10 22...
Page 309: ...13 Mechanical Diagnosis TK 482 TK 486 and TK 486V Engines 13 2...
Page 316: ...Mechanical Diagnosis 13 8...
Page 322: ...Refrigeration System Diagnosis 14 6...
Page 332: ...Single Temperature Refrigeration System Diagrams 15 10...
Page 339: ...Multi Temperature Refrigeration System Diagrams 16 7...
Page 340: ...Multi Temperature Refrigeration System Diagrams 16 8...