Application Software APSW 2795
12.5
Tab Sheet MEASURE
The tab sheet MEASURE is split into five parts.
Display of Measurement Values
At the top of the window the actual measurement values are displayed including vector group, test voltage, voltage
ratio, ratio deviation and phase deviation.
Control of Test Voltage and Tap Changer
The editable elements in the middle section are used to specify the test voltage, the tap changer position and - if
tertiary winding exists – the windings between which the ratio should be measured.
In the example shown above the ratio between the tap position T1 of the high voltage and the middle tap position T0
of the low-voltage winding will be measured with a voltage of 40 V. Only the taps, which have been activated and
defined in Menu “Trafo Data” can be selected.
Control of Test Procedure
At the bottom of the window the buttons for start and stop a measurement are shown. If a test is started by clicking
“Test a Single Tap” the program adopts the selected tap changer position and performs a ratio measurement at the
selected tap position. If “Start Testing all Taps” is selected the instrument will start at the selected tap and run through
the others.
Display of Test Progress and Measurement Status
As on the instrument itself a “Progress” bar shown at the left side under the voltage selection dialog indicates the
actual test progress of the measurement.
Summary of Contents for TTR 2795
Page 1: ...Operating Instructions HAEFELY TEST AG TTR 2795 Transformer Turns Ratio Meter Version 1 4 ...
Page 10: ...6 Introduction Maximum Roll Diameter Outer 50mm Inner 10mm ...
Page 22: ...18 Connection and Setup Figure 11 Connecting to three phase BCT ...
Page 101: ...Application Software APSW 2795 97 ...
Page 111: ...Miscellaneous 107 14 7 Conformity ...