![Siemens SINAMICS G120C Operating Instructions Manual Download Page 137](http://html.mh-extra.com/html/siemens/sinamics-g120c/sinamics-g120c_operating-instructions-manual_376473137.webp)
5. When the USB interface is appropriately set, then the "Accessible nodes" screen form
shows the inverters that can be accessed.
Figure 5-13 Inverters found in STARTER
Figure 5-14 Inverters found in Startdrive
If you have not correctly set the USB interface, then the following "No additional nodes
found" message is displayed. In this case, follow the description below.
6. Further procedure dependent on the commissioning software used:
– STARTER:
- Select the inverter ☑.
- Press the "Accept" button.
– Startdrive:
Transfer the inverter into the project using the menu: "Online - Upload device as new
station (hardware and software)".
You have transferred an inverter accessible via the USB interface into your project.
Commissioning
5.5 Quick commissioning with a PC
SINAMICS G120C converter
Operating Instructions, 09/2017, FW V4.7 SP9, A5E34263257B AF
137