Palletizing Solution - Instruction Manual
3. Position the robot so that the wrist is on the outside left side of the base like shown in the figure below.
4. Move the robot so the robot tool flange is parallel to the ground: change the feature reference to Base and modify the tool pos-
ition like the following: RX=0°, RY= 180°, RZ=0°.
5. Modify the Tool Position X value (base reference) to 333.35 mm (Make sure the TCP is set to 0 (the TCP menu can be found
in the Installation tab.))
Warning
Move the robot slowly and watch the movement to avoid collisions.
6. Rotate the column clockwise so that the side of the robot wrist touches the side of the base.
7. Tighten the four (4) screws to secure the column onto the base. Torque must be 50 Nm.
8. On the teach pendant, validate that the X value is still 333.35 mm.
9. Put the robot back in position of use.
38
Summary of Contents for PALLETIZING SOLUTION AX Series
Page 4: ...Palletizing Solution Instruction Manual 4 ...
Page 14: ...Palletizing Solution Instruction Manual 14 ...
Page 21: ...Palletizing Solution Instruction Manual 21 ...
Page 33: ...Base Cover Plate 1 Remove the cover plate that will allow the cable management 33 ...
Page 84: ...6 1 2 AirPick Vacuum Gripper Fig 6 1 AirPick general dimensions 84 ...
Page 85: ...Palletizing Solution Instruction Manual 6 1 3 Extra Reach Bracket 85 ...
Page 86: ...6 1 4 Bracket for Two 2 Suction Cups Fig 6 2 Two air nodes bracket s dimensions 86 ...
Page 113: ...12 2 Safety Connections Fig 12 2 Universal Robots Controller Safety Connections Schema ...