LubriMist
®
Model IVT
Oil Mist Generating System
Installation and Operating Manual
Page 75
of 256
Cabinet Cooling
For NEC Constructions
The IVT Oil Mist Generator cabinet cooling system uses the compressed instrument air supply
connected to the IVT Oil Mist Generator to operate. To commission the cabinet cooling system:
A. Insure that the IVT Oil Mist Generator has been commissioned and operating so that the air
supply block valve to the IVT is in the full open position.
B. Open the air supply block valve to the IVT Oil Mist Generator cabinet cooling system.
C. Using the air pressure regulator, adjust the regulated air pressure to the vortex cold air
generator to 90 PSIG ( 6 Bar ).
D. Ensure that the IVT Oil Mist Generator cabinet doors are closed and that the door latch is
secured in the closed position.
Open Air Supply
Block Valve
Adjust Pressure
Regulator To
Proper setting
Pressure Gauge
Monitors Pressure
Setting