A4 Operating Sequence
Step 1
Climbing enclosure is in position.
Close cover flaps.
Concrete the columns.
Step 2
Erect slab formwork with stopends.
Install leading anchor with the aid of
the Slab Anchor Template.
Fig. A4.01
Fig. A4.02
Operating Sequence
The difference in the operating
sequence of Versions 1 - 3 and 4 is
primarily due to when the slab is
struck.
All versions can be climbed using the
hydraulic self-climbing device or by
crane.
Version 1 - 3
Climbing enclosure with working plat-
form.
The slab formwork is in the way for the
climbing procedure. PERI recommends
a slab formwork system, e.g.
SKYDECK, which allows early striking.
The example shows the operating
sequence with SKYDECK Slab Form-
work.
RCS P Climbing Protection Panel
Instructions for Assembly and Use – Standard Configuration
Summary of Contents for RCS P
Page 13: ...13 RCS P Climbing Protection Panel Instructions for Assembly and Use Standard Configuration...
Page 93: ...93 RCS P Climbing Protection Panel Instructions for Assembly and Use Standard Configuration...
Page 101: ...101 RCS P Climbing Protection Panel Instructions for Assembly and Use Standard Configuration...
Page 169: ...169...