646 Chapter 17 Hardware procedures
241-1501-240 5.2S2
•
You must be familiar with “Safety considerations and best practices”
(page 53).
•
Prepare the far-end traffic for the impact of taking one or two
Passport 15000 or 20000 nodes out of service.
•
Switching off the breakers in sequence protects the equipment from
damage.
Procedure steps
1
Locate the BIM to be powered off.
When powering down an entire Passport 15000 or 20000 node, locate the
mate BIM for the switch.
2
Switch off each breaker one at a time from left to right, excluding the
middle breaker. Switch off a breaker by pressing in the O symbol.
3
When the mate BIM is also to be powered down, switch off each breaker
one at a time from left to right, excluding the middle breaker.
4
When two nodes are to be powered down, repeat step 1 to step 3.
5
When the entire BIP is powered down to enable work on switch hardware
units (for example, removing a shelf assembly), wait 10 minutes for the
fans to continue cooling down the unpowered circuit cards.
6
Switch off the middle breakers one at a time from left to right. The fan
blades in the cooling units take a while to slow down.
When all BIM breakers off and the input feeds are still powered to the BIP,
the BIM LEDs are still lit.
7
Check the status LEDs of all plug-ins of the shelf assembly. Ensure that
no LEDs are lit on:
•
both CPs and all FPs at the front
•
the 2 fabrics at the rear
•
the 4 PIMs at the rear of a Passport 20000 (a Passport 15000 does
not have PIM LEDs)
Summary of Contents for Passport 15000
Page 1: ...Passport 15000 20000 Hardware Installation Maintenance and Upgrade 241 1501 240 ...
Page 2: ......
Page 4: ......
Page 6: ...6 Publication history 241 1501 240 5 2S2 ...
Page 32: ...32 Contents 241 1501 240 5 2S2 ...
Page 48: ...48 About this document 241 1501 240 5 2S2 ...
Page 52: ...52 Chapter 1 Overview of hardware tasks 241 1501 240 5 2S2 ...
Page 70: ...70 Chapter 2 Safety considerations and best practices 241 1501 240 5 2S2 ...
Page 84: ...84 Chapter 4 Alarm BITS module 241 1501 240 5 2S2 ...
Page 94: ...94 Chapter 5 CP and FP cables 241 1501 240 5 2S2 ...
Page 178: ...178 Chapter 11 Initial switch hardware installations 241 1501 240 5 2S2 ...
Page 182: ...182 Chapter 12 MAC address module 241 1501 240 5 2S2 ...
Page 216: ...216 Chapter 14 Power and ground hardware of a Passport 15000 or 20000 241 1501 240 5 2S2 ...
Page 872: ...872 Chapter 17 Hardware procedures 241 1501 240 5 2S2 ...
Page 873: ......