7 Commissioning
Maschinenfabrik Reinhausen GmbH 2020
74
3587317/21 EN
TAPCON
®
7 Commissioning
You need to set several parameters and perform function tests before com-
missioning the device. These are described in the following sections.
NOTICE
Damage to device and system periphery
An incorrectly connected device can lead to damage to the device and sys-
tem periphery.
► Check the entire configuration before commissioning.
7.1 Performing tests
Please contact Maschinenfabrik Reinhausen GmbH (MR) if any aspect of
the tests is not clear.
7.1.1 Ground test
For commissioning, carry out a ground test (check of the impedance of the
protective bonding) in accordance with IEC 61010-1. Note the following in-
formation:
▪ Test current: 2 times the measurement current of the overcurrent protec-
tion device of the supply line.
▪ Test duration: 1 minute for each measurement point.
▪ The measured voltage between the measurement point and the protective
conductor must be smaller than 10 V.