Site I/O , Span Line, RGPS and Modem Cabling for Sites Equipped With
Customer–Supplied Site I/O Interface
– continued
DEC 2000
4-25
SC
t
300 BTS Hardware Installation, ATP and FRU Procedures
PRELIMINARY
Procedure to Install Site I/O
Cable Between Site I/O
Junction Box and Site I/O
Interface
Route the Site I/O junction box cable from the unit location(s) to the Site
I/O Extender Cable (cable Z). Route cable Z to the Site I/O interface.
Connect the appropriate connectors within the Site I/O interface. Refer
to Figure 4-15 and Table 4-25.
If lightning arrestors are required, they must be customer–supplied.
Lightning arrestors are not necessary for sites equipped with optional
Primary Surge Suppressor.
Figure 4-15: Site I/O Cabling Details (MicroCell Unit Shown)
CUSTOMER
INPUTS
SPAN
RGPS
PHONE(MODEM)
SITE I/O
INTERFACE
SITE I/O
JUNCTION BOX
SITE I/O
CABLE
M
N
O
V
Z
DEUTSCH
CONNECTOR
4