6-4
PMP320HDW2v1
Preliminary
JUL 2010
Pre-installation planning
Chapter 6: Connectorized CSM Hardware Installation
Pre-installation planning
While on the ground, find an appropriate location outside the building to mount the CSM.
NOTE
To provide Internet service, the CSM communicates with a base station on the
communications tower of the service provider. Information about the nearest
communications tower is provided by the service provider. For example, if the tower
nearest to the building is towards the north of the building, install the CSM on the
north side of the building.
After determining the optimal side of the building, select an CSM mounting point at a high
location on the building such as under the eaves.
Components shipped with the CSM
Locate the components shipped with the CSM device. The parts list for the CSM installation
consists of the following items:
Table 6-1 CSM parts list
Component
Quantity
CSM 320 device
1
Bracket base mounting
1
Bracket Bottom Mounting
1
Bracket Top Mounting
1
Middle mounting bracket
1
M8 (50 mm) hex head bolt
2
M8 (100 mm) bolt
2
M8 split washer
13
M8 washer
11
M8 nut
3
M5 (35 mm) set screw
2
M4 (16 mm) bolt
4
M4 split washer
4
M4 washer
4
Dsign power supply
1
ENET cable
1
Summary of Contents for PMP 320
Page 8: ...Preliminary JUL 2010 iv PMP320HDW2v1 ...
Page 31: ......
Page 78: ...Preliminary JUL 2010 Chapter 4 Cables ...
Page 85: ......
Page 133: ...PMP320HDW2v1 7 31 JUL 2010 Preliminary Chapter 8 Regulatory Legal and Safety Notices ...