RS485 Modbus settings:
n
Baud rate: 9600
n
Word length: 8 Bit
n
Stop bit: 1 Bit
n
Parity: None
n
You can read out a maximum of 40 addresses at once.
The list of Modbus commands can be found in section 13 „Modbus ad-
dresses“ on page 51.
Perform the following work steps:
1.
Open the device housing.
2.
Connect a two-wire cable to terminals A and B of the RS485 module.
3.
Connect the device with your network.
ü
Device connected with network.
7.13 Installing the sensors
7.13.1 Disinfection measuring cell
The DMZ3.1 measuring cell for measuring the degree of disinfection (free
chlorine) must be connected directly in the housing of the
TOPAX
®
MC
controller. The counter electrode is already installed in the fitting and con-
nected with the controller.
Pre-conditions for actions:
ü
The installation of the water sampling station, the electrics and the
hydraulics has been performed successfully.
ü
The measuring cells documentation is within easy reach.
Perform the following work steps:
1.
Unscrew the protective caps from the top of the valves and store
these away carefully for future use.
2.
Screw the measuring cells (Fig. 2 „Water sampling station EASYPRO
4“ on page 10, pos. 7) into the fittings. Observe the measuring cell
documentation during installation.
3.
Connect the measuring cells with the connecting cables.
ü
The disinfection measuring cell has been installed successful-
ly.
7.13.2 Measuring cells Redox value, pH value and
conductivity
The connecting cables are already installed on the
TOPAX
®
MC
controller
and need only be connected to the measuring cells.
Pre-conditions for actions:
ü
The installation of the water sampling station, the electrics and the
hydraulics has been performed successfully.
ü
The measuring cells documentation is within easy reach.
Perform the following work steps:
1.
Unscrew the protective caps from the top of the valves and store
these away carefully for future use.
2.
Screw the measuring cells (Fig. 2 „Water sampling station EASYPRO
4“ on page 10, Pos. 7 – 10) into the fittings. Observe the measur-
ing cell documentation during installation.
3.
Connect the measuring cells with the connecting cables.
ü
The measuring cells of the water sampling station have been
successfully installed.
7.13.3 Temperature sensor
The flow controller DFR 45 is fitted with a temperature sensor (Pt100)
which is already installed in the
TOPAX
®
MC
controller. This section de-
scribes how to replace the sensor.
Pre-conditions for actions:
ü
The installation of the water sampling station, the electrics and the
hydraulics has been performed successfully.
Perform the following work steps:
1.
Unscrew the sensor or the sealing plugs from the flow controller tem-
perature measuring station.
2.
Screw the new temperature sensor into the opening.
3.
Open the housing of the
TOPAX
®
MC
controller.
4.
Connect the connecting cable of the temperature sensor with the
clamps 57 and 58.
5.
Lead the connecting cable through one of the cable screw connec-
tions on the underside of the controller and screw it tight to guaran-
tee the protection class of the housing.
6.
Close the housing of the
TOPAX
®
MC
controller.
ü
The temperature sensor of the water sampling station has been
installed successfully.