Page 13 Leica EM TIC 3X Operating Manual 07/17
2.9.3 Safety measures at the installation site
The following measures must be implemented to prevent incorrect use at the
installation site:
•
The electrical and gas connections for the system must be carried out by
qualified technicians.
•
Gas bottles must be stood up securely and connected professionally. The
system must be connected to the operator's mains supply by qualified
technicians.
•
The system must not be operated except by trained and authorized personal.
•
Repairs may only be made by authorized staff of Leica representatives.
•
If the Leica EM TIC 3X Triple Ion Beam Cutter system is installed incorrectly,
the system may be damaged.
2.9.4 Safety measures before use
The Leica EM TIC 3X Triple Ion Beam Cutter system must be installed by authorized
staff of Leica representatives.
Note!
The system should be switched off for maintenance and servicing only, not at
the end of a work session.
The system must be installed correctly before it is commissioned by the technical
service. The supply of power and gas must be assured according requirements
described at point 3.
2.9.5 Qualification of operating personnel
The operating personnel must be familiar with and follow the recognized provisions
for safety at work.
The operating personnel must be trained and familiar with the duties that have been
assigned to them and for which they are responsible.
The professional profiles for operating personnel responsible for the system are
outlined in the following.