3. COMPLETING WORK
If the coolant has been drained, tighten the drain valve, and add water to the specified level. Run
the engine to circulate the water through the system. Then check the water level again.
If the hydraulic equipment has been removed and installed again, add engine oil to the specified
level. Run the engine to circulate the oil through the system. Then check the oil level again.
If the piping or hydraulic equipment, such as hydraulic cylinders, pumps, or motors, have been
removed for repair, always bleed the air from the system after reassembling the parts.
Add the specified amount of grease (molybdenum disulphied grease) to the work equipment
related parts.
1)
2)
3)
4)
Summary of Contents for HX145 LCR
Page 11: ...SECTION 1 GENERAL SECTION 1 GENERAL Group 1 Safety Hints 1 1 Group 2 Specifications 1 10...
Page 204: ...4 5 MEMORANDUM HYUNDAI HEAVY INDUSTRIES CO LTD CONSTRUCTION EQUIPMENT DIV...
Page 627: ...8 155 125LCR8TM30 Turn casing 1 upside down and remove oil seal 3 using jig 29...
Page 657: ...8 185 8 185 Remove lock nut 22 and then boot 23 14 36078RL14 2507ARL10...