FusionModule800 Smart Small Data Center
Installation Guide (Six Fans)
3 Hardware Installation
Issue 10 (2019-12-20)
Copyright © Huawei Technologies Co., Ltd.
164
If two smart ETH gateways are configured, install them in positions shown in
If three smart ETH gateways are configured, install two of them in positions shown in
, and install the remaining one on the M-shaped cable trough of an adjacent
cabinet.
Figure 3-186
Position 1 for installing a smart ETH gateway
(1) Smart ETH gateway
If M-shaped cable troughs are not deployed for the Smart Module, install the smart ETH
gateway on the top of the Converged Cabinet, as shown in