FusionModule800 Smart Small Data Center
Installation Guide (Six Fans)
3 Hardware Installation
Issue 10 (2019-12-20)
Copyright © Huawei Technologies Co., Ltd.
30
Figure 3-5
Installing ramps
6.
Raise the six leveling feet to the highest point using an adjustable wrench, and push the
cabinet to the installation position over castors.
----End
3.1.2 Smart Cooling Product Transportation and Unpacking
Only trained personnel are allowed to move the equipment. Use a pallet truck to move the
equipment with its case down from the transportation truck. The forks must be properly
positioned to ensure that the equipment does not topple.
To avoid toppling, secure the equipment to the pallet truck before moving it, and assign
persons to watch out the equipment during movement.
Move the cabinet with caution. Any bumping or falling may damage the equipment.
Move the equipment close to the installation position before unpacking. Unpack the
equipment with caution to avoid scratching or bumping. Take down the equipment from
the pallet only immediately before installation.
Unpacking the Indoor Unit
Step 1
Verify that the indoor unit package is intact. If any damage is found, notify the carrier
immediately.
Step 2
Remove the package.
1.
Remove the straps, outer packing materials, cushioning materials, and then plastic film.
2.
Check that the indoor unit exterior is intact and free of collision and scratches. If any
damage is found, notify the carrier immediately.