FusionModule800 Smart Small Data Center
Installation Guide (Six Fans)
4 Cable Routing
Issue 10 (2019-12-20)
Copyright © Huawei Technologies Co., Ltd.
216
Figure 4-31
Connecting input power cables to the 3 U PDU
(1) Input power cable
----End
4.5.2 Bottom Cable Routing
Cables connect to the same positions on the power distribution subrack irrespective of
whether cables are routed through the top or bottom of the Converged Cabinet, but the cable
routes inside the cabinet are different. This section describes how to connect the input power
cable to the 7.5 kW 3 U PDU in the bottom cable routing scenario for the Converged Cabinet.
shows the cable holes for routing cables through the bottom of the Converged
Cabinet.