FusionModule800 Smart Small Data Center
Installation Guide (Six Fans)
6 Power-On Commissioning
Issue 10 (2019-12-20)
Copyright © Huawei Technologies Co., Ltd.
266
Check that the cables to the indoor and outdoor units are correctly connected and that the
live wire, neutral wire, and ground cable are correctly connected.
Ensure that the smart cooling product circuit breaker in the upstream PDB is OFF.
Verify that the indoor unit power cable is correctly connected and that the input voltage
meets requirements.
Check that the smart cooling product control unit and the ECC800 or smart ETH
gateway are correctly connected.
Context
The outdoor unit circuit breaker is ON by default. The stop valves on the gas pipe and liquid
pipe for the outdoor unit are open.
Procedure
Step 1
Switch on the circuit breakers for the indoor and outdoor units on the upstream PDB.
The electric heating belt of the crankcase starts working. Before starting the compressor,
ensure that the electric heating belt of the crankcase has been preheated for more than 12
hours. Otherwise, Huawei will not repair the compressor.
Step 2
Commission the system after the electric heating belt of the crankcase has been preheated for
12 hours.
----End
6.4.2 Initial Configuration
6.4.2.1 Setting Temperature and Humidity
Procedure
Step 1
Log in to the ECC800 WebUI as user
admin
.
Step 2
Choose
Monitoring
>
Air Conditioner
>
NetCol5000-A0101
>
Running Parameters
>
Temp/Hum Sensor Para
to view temperature and humidity parameters.
0101
in
NetCol5000-A0101
is variable and subject to changes with the smart cooling product
connection sequence. The displayed value prevails.
Step 3
Enable the T/H sensor connected to the smart cooling product.
Assume that one smart cooling product is configured for three cabinets. Three T/H sensors whose
addresses are 11, 12, and 21 connect to smart cooling product 1. Set cold-aisle sensor 1, cold-aisle
sensor 2, and hot-aisle sensor 1 to
Enable