FusionModule1000B Water-Cooled IT Solution
Commissioning Guide
7 System Commissioning
Issue 02 (2017-01-10)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
45
When the RH2288 server switches between the two power supplies, if the server does not restart or
break down, the power supply switchover meets the requirements.
----End
7.1.2 Commissioning the Logic Load Disconnection
(Powering-Off) of the Power Supply System Under Normal
Temperature
Prerequisites
The FusionModule1000 is powered on, commissioned, and working properly.
Preparations
Tools: none
Documents: power supply and distribution system diagrams, power supply and distribution
component layout
Skill requirement: power distribution system engineer
For the diagrams, see the initial configuration parameter manual for the solution in use.
Procedure
Step 1
Power off the FusionModule1000 by referring to
8 Shutting Down and Powering Off
Save parameters before power-off.
Power off the devices in the normal power-off logic sequence.
Step 2
Verify whether the system and components are intact and working properly.
If no, locate and rectify the fault. Then go to
Step 3
Power off the FusionModule1000 by following instructions in
Step 4
Verify whether the systems run stably after power-on.
The FusionModule1000 meets requirements if its components are intact and systems are normal after
powered off, and systems run stably after power-on.
----End