FusionModule1000B Water-Cooled IT Solution
Commissioning Guide
1 Precautions for Power-On Commissioning
Issue 02 (2017-01-10)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
1
1
Precautions for Power-On Commissioning
Verify that the configurations of various systems in the FusionModule1000 are consistent
with the initial configuration parameter manual.
This manual describes how to perform power-on commissioning. For details about
drawings and initial configuration parameters required during the operation, see the
initial configuration parameter manual for the solution in use.
Conduct power-on commissioning only after the FusionModule1000 is installed and the
installation is verified.
Power-on commissioning for each specific system must be performed under instructions
from qualified engineers.
The initial configuration parameters are essential to the reliable running of all systems.
Improper modifications of parameters may cause abnormal running status, or even
damage to the systems.
The initial parameters of the FusionModule1000 are configured before delivery. For
details about how to modify the parameters, see the documents delivered with the
components and the actual solution configuration.
Prior to the power-on commissioning, remove all the protective devices installed for
transporting the FusionModule1000, such as the securing tape on the smoke detectors,
heat detectors, and T/H sensors.
Before power-on commissioning, verify that the aisle temperature is within the normal
working range.
Do not perform power-on commissioning during a thunderstorm.
Verify that the upstream power supply is continuous during power-on commissioning.
Operations marked as optional in chapters, sections, or procedures can be performed
depending on the actual situation.
Huawei assumes no liability for any loss caused by unauthorized changes to the initial
configuration parameters.